Recently Completed Projects

SNGPL commissioned 203 km transmission pipelines (including 52 km for M/s MOL on contract) and 5446 km distribution lines in FY2010-11. Thus gas facility was extended to various localities/towns and industrial units across Punjab and Khyber Pakhtunkhwa. Highlights of Projects completed include as under:-

  • 12 inch dia x 47 km Mandi Bahauddin transmission pipeline was commissioned to improve gas pressure in SNGPL's network from Lala-Musa towards Jehlum.
  • The completion of Qadirpur compression project is yet another milestone which was achieved by SNGPL. This project enhanced the overall capacity of the Qadirpur gas field by 100 MMCFD. SNGPL takes pride for completing it on time in the face of challenging constraints and tight schedule.
  • SNGPL completed various flowlines as a contractor for MOL Pakistan including 12 inch dia x 19.7 km Maramzai Flow line, 8 inch dia x 14.7 km Mamikhel-1 flow line, 8 inch dia x 10.1 km AV1-AV2 Trunk line and 8 inch dia x 5.40 km M8-VA1 flowline. The completion and commissioning of this gas gathering network helped secure additional 85 Million Cubic Feet Per Day (MMCFD) to SNGPL's transmission system.

 

Updated: 12-06-2017